Overall Rating | Silver - expired |
---|---|
Overall Score | 47.51 |
Liaison | Mike Evans |
Submission Date | Feb. 2, 2016 |
Executive Letter | Download |
Williams College
OP-24: Construction and Demolition Waste Diversion
Status | Score | Responsible Party |
---|---|---|
0.95 / 1.00 |
Mike
Evans Assistant Director Zilkha Center for Environmental Initiatives |
"---"
indicates that no data was submitted for this field
None
Construction and demolition materials recycled, donated, or otherwise recovered:
7,728
Tons
None
Construction and demolition materials landfilled or incinerated :
444
Tons
None
A brief description of programs, policies, infrastructure investments, outreach efforts, and/or other factors that contributed to the diversion rate for construction and demolition waste:
All new construction and major renovation projects on campus either pursue LEED or Living Building Challenge certification. Both programs have guidelines that encourage or require 50-100% of construction and demolition waste be recycled or salvaged.
Data source(s) and notes about the submission:
---
The information presented here is self-reported. While AASHE staff review portions of all STARS reports and institutions are welcome to seek additional forms of review, the data in STARS reports are not verified by AASHE. If you believe any of this information is erroneous or inconsistent with credit criteria, please review the process for inquiring about the information reported by an institution or simply email your inquiry to stars@aashe.org.