Status Score Responsible Party
Complete 0.70 / 7.00 David Cajigas
Senior Director, University Operations Services
University Operations
"---" indicates that no data was submitted for this field

Option 1: Total clean and renewable electricity generated on site during the performance year and for which the institution retains or has retired the associated environmental attributes :
244.17 MMBtu

Option 2: Non-electric renewable energy generated:
2,407.70 MMBtu

Option 3: Total clean and renewable electricity generated by off-site projects that the institution catalyzed and for which the institution retains or has retired the associated environmental attributes :
0 MMBtu

Option 4: Total RECs and other similar renewable energy products that the institution purchased during the performance year that are Green-e certified or meet the Green-e standard's technical requirements and are third party verified:
76,810.94 MMBtu

Option 5: Total electricity generated with co-generation technology using non-renewable fuel sources :
0 MMBtu

Total energy consumed during the performance year :
219,444.15 MMBtu

A brief description of on-site renewable electricity generating devices :

50 kW solar array on the roof of the facilities building.


A brief description of on-site renewable non-electric energy devices:

Solar thermal panels on the rooftops of Benson and several residence halls.


A brief description of off-site, institution-catalyzed, renewable electricity generating devices:

n/a


A brief description of RECs or other similar renewable energy products purchased during the previous year:

SCU purchased 22,512 mWh of green power from Silicon Valley Power in FY 2010.


A brief description of co-generation technologies deployed:

n/a


The website URL where information about the institution's renewable energy sources is available:
Data source(s) and notes about the submission:

Performance year: calendar year 2009.

In 2010, SCU installed a 10 kW wind turbine on the roof of the Support Services Building, as well as a 1 mW photovoltaic array on the Leavey Activities Center, Malley Fitness Center, and the Parking Structure.


Performance year: calendar year 2009.

In 2010, SCU installed a 10 kW wind turbine on the roof of the Support Services Building, as well as a 1 mW photovoltaic array on the Leavey Activities Center, Malley Fitness Center, and the Parking Structure.

The information presented here is self-reported. While AASHE staff review portions of all STARS reports and institutions are welcome to seek additional forms of review, the data in STARS reports are not verified by AASHE. If you believe any of this information is erroneous or inconsistent with credit criteria, please review the process for inquiring about the information reported by an institution or simply email your inquiry to stars@aashe.org.