Overall Rating | Bronze - expired |
---|---|
Overall Score | 37.63 |
Liaison | Emma Shipalesky |
Submission Date | March 23, 2012 |
Executive Letter | Download |
Northern Alberta Institute of Technology
OP-T2-18: Energy Metering
Status | Score | Responsible Party |
---|---|---|
0.00 / 0.25 |
Robert
Akkerman Acting Director Maintenance and Operations |
"---"
indicates that no data was submitted for this field
None
Does the institution meter all energy consumption (electricity, natural gas, purchased steam, etc.) for at least one building?:
No
None
A brief description of the metering system:
All utilities are metered at the central plant (heating and cooling) no sub-metering of energy as it applies to individual buildings.
None
The website URL where information about the metering system is available:
---
Data source(s) and notes about the submission:
---
The information presented here is self-reported. While AASHE staff review portions of all STARS reports and institutions are welcome to seek additional forms of review, the data in STARS reports are not verified by AASHE. If you believe any of this information is erroneous or inconsistent with credit criteria, please review the process for inquiring about the information reported by an institution or simply email your inquiry to stars@aashe.org.