Construction and demolition materials recycled, donated, or otherwise recovered:
13.47
Tons
Construction and demolition materials landfilled or incinerated:
13.47
Tons
Percentage of construction and demolition materials diverted from the landfill or incinerator through recycling, donation and/or other forms of recovery:
50
Optional Fields
50% of construction debris must be diverted from landfills per contracts with construction companies
Website URL where information about the institution’s C&D waste diversion efforts is available:
---
Additional documentation to support the submission:
---
Data source(s) and notes about the submission:
data taken from Bertolotti invoices for 20-21 (performance year).
per Judy Lanchester, contracts for construction debris removal specify that atleast 50% must be recycled. So we used 50% of the total amount hauled by Bertolotti (26.94 tons) which we determined by going through invoices from Bertolotti.
per Judy Lanchester, contracts for construction debris removal specify that atleast 50% must be recycled. So we used 50% of the total amount hauled by Bertolotti (26.94 tons) which we determined by going through invoices from Bertolotti.
The information presented here is self-reported. While AASHE staff review portions of all STARS reports and institutions are welcome to seek additional forms of review, the data in STARS reports are not verified by AASHE. If you believe any of this information is erroneous or inconsistent with credit criteria, please review the process for inquiring about the information reported by an institution or simply email your inquiry to stars@aashe.org.