Overall Rating Silver
Overall Score 60.18
Liaison Martín Sanchez
Submission Date June 29, 2024

STARS v2.2

Tecnológico de Monterrey – Campus Querétaro
OP-5: Building Energy Efficiency

Status Score Responsible Party
Complete 4.39 / 6.00
"---" indicates that no data was submitted for this field

Electricity use, performance year (report kilowatt-hours):
kWh MMBtu
Imported electricity 5,030,798 Kilowatt-hours 17,165.08 MMBtu
Electricity from on-site, non-combustion facilities/devices (e.g., renewable energy systems) 0 Kilowatt-hours 0 MMBtu

Stationary fuels and thermal energy, performance year (report MMBtu):
MMBtu
Stationary fuels used on-site to generate electricity and/or thermal energy 384.20 MMBtu
Imported steam, hot water, and/or chilled water 0 MMBtu

Total site energy consumption, performance year:
17,549.28 MMBtu

Gross floor area of building space, performance year:
3,607,127.28 Gross square feet

Floor area of energy intensive space, performance year:
Floor area
Laboratory space 144,558.89 Square feet
Healthcare space 1,061.32 Square feet
Other energy intensive space 4,203.63 Square feet

EUI-adjusted floor area, performance year:
3,902,571.33 Gross square feet

Degree days, performance year:
Degree days
Heating degree days 261 Degree-Days (°F)
Cooling degree days 3,384 Degree-Days (°F)

Total degree days, performance year:
3,645 Degree-Days (°F)

Start and end dates of the performance year (or 3-year period):
Start date End date
Performance period Jan. 1, 2023 Dec. 31, 2023

Total site energy consumption per unit of EUI-adjusted floor area per degree day, performance year:
1.23 Btu / GSF / Degree-Day (°F)

Electricity use, baseline year (report kWh):
kWh MMBtu
Imported electricity 5,727,008 Kilowatt-hours 19,540.55 MMBtu
Electricity from on-site, non-combustion facilities/devices (e.g., renewable energy systems) 0 Kilowatt-hours 0 MMBtu

Stationary fuels and thermal energy, baseline year (report MMBtu):
MMBtu
Stationary fuels used on-site to generate electricity and/or thermal energy 1,313 MMBtu
Imported steam, hot water, and/or chilled water 0 MMBtu

Total site energy consumption, baseline year:
20,853.55 MMBtu

Gross floor area of building space, baseline year:
3,210,220 Gross square feet

Start and end dates of the baseline year (or 3-year period):
Start date End date
Baseline period Jan. 1, 2019 Dec. 31, 2019

A brief description of when and why the energy consumption baseline was adopted:
---

Source-site ratio for imported electricity:
2.50

Total energy consumption per unit of floor area:
Site energy Source energy
Performance year 0.00 MMBtu per square foot 0.01 MMBtu per square foot
Baseline year 0.01 MMBtu per square foot 0.02 MMBtu per square foot

Percentage reduction in total source energy consumption per unit of floor area from baseline:
23.19

Documentation to support the performance year energy consumption figures reported above:
---

A brief description of the institution's initiatives to shift individual attitudes and practices in regard to energy efficiency:

https://tec.mx/sites/default/files/repositorio/sentido-humano/sostenibilidad/ruta-azul/reportes/ReportRutaAzul-CompleteVersion-3.pdf


A brief description of energy use standards and controls employed by the institution:
---

A brief description of Light Emitting Diode (LED) lighting and other energy-efficient lighting strategies employed by the institution:
---

A brief description of passive solar heating, geothermal systems, and related strategies employed by the institution:
---

A brief description of co-generation employed by the institution:
---

A brief description of the institution's initiatives to replace energy-consuming appliances, equipment, and systems with high efficiency alternatives:
---

Website URL where information about the institution’s energy conservation and efficiency program is available:
---

Additional documentation to support the submission:
---

Data source(s) and notes about the submission:
---

The information presented here is self-reported. While AASHE staff review portions of all STARS reports and institutions are welcome to seek additional forms of review, the data in STARS reports are not verified by AASHE. If you believe any of this information is erroneous or inconsistent with credit criteria, please review the process for inquiring about the information reported by an institution or simply email your inquiry to stars@aashe.org.