Overall Rating | Silver - expired |
---|---|
Overall Score | 47.69 |
Liaison | David Petree |
Submission Date | June 4, 2012 |
Executive Letter | Download |
Guilford College
OP-19: Construction and Demolition Waste Diversion
Status | Score | Responsible Party |
---|---|---|
0.25 / 1.00 |
Dan
Young Director of Facilities Engineering Operations & Facilities Services |
"---"
indicates that no data was submitted for this field
Amount of construction and demolition materials recycled, donated, or otherwise recovered :
6
Tons
Amount of construction and demolition materials landfilled or incinerated :
18
Tons
A brief description of programs, policies, infrastructure investments, outreach efforts, and/or other factors that contribute to the diversion rate for construction and demolition waste:
Guilford College is trying to reuse 100% of everything is removed or recovered through construction debris to minimize our waste stream.
Data source(s) and notes about the submission:
---
The information presented here is self-reported. While AASHE staff review portions of all STARS reports and institutions are welcome to seek additional forms of review, the data in STARS reports are not verified by AASHE. If you believe any of this information is erroneous or inconsistent with credit criteria, please review the process for inquiring about the information reported by an institution or simply email your inquiry to stars@aashe.org.