PAE-5: Climate Action Plan
Status | Score | Responsible Party |
---|---|---|
2.00 / 2.00 |
Mary
Whitney University Sustainability Coordinator Office of Sustainability |
"---"
indicates that no data was submitted for this field
None
Does the institution have a plan to mitigate its greenhouse gas emissions that meets the criteria for this credit?:
Yes
None
A brief summary of the climate plan’s long-term goals:
Climate neutrality by 2025
None
A brief summary of the climate plan’s short-term goals:
Chatham has identified high-priority projects to show an actual reduction in our carbon footprint. They have been assigned a priority, based on costs, ROI and carbon reduction.
#1. Enhanced Metering and Power Quality: Completed energy audit of the main campus and Eastside suggests energy management systems units could be installed in each building at a cost of $55,295 with an energy savings of 387,650 kWh and a cost savings of approximately $48,486 including demand savings.
#2. Lighting Efficiency Upgrade
The lighting fixtures in many campus buildings can be upgraded to T8 ballasts. Replacement high efficiency electronic ballast will cost approximately $96,800.00, with an anticipated energy savings of 616,711 kWh and a cost savings of approximately $60,999.00. This project estimate includes both demand savings and occupancy sensors.
The motor controls and lighting upgrades projects would, when fully implemented, show an estimated 10% annual real reduction in emissions, within a maximum 4-year ROI time frame.
#3. Photovoltaic Power - 50 kW Array on the Eastside Building
The array would consist of high efficiency PV panels with array combiners, a DC/AC inverter; disconnect switches and an isolation transformer. Cost estimates: around $408,000.00 to install, yield 85,600 kWh annually at a savings of $11,124.00 per year.
#4. Centralized Geothermal Co-generation
On the Shadyside campus, we plan to consolidate all heating and cooling into one centralized natural-gas fired co-generation plant. The plant’s three megawatt co-generation plant would be located in the center of the quad below grade. Co-generation units would provide electricity to upper campus grid via new connections. We are also planning for a natural gas cogeneration / geothermal system to be located under the parking lot at Eastside. Preliminary numbers show an estimated cost of $3-5 million dollars, with estimated reduction of 15,000,000 kWh, about $1 million saved annually.
None
Year the climate plan was formally adopted or approved:
2,009
None
An indication of whether institution has made a commitment to reduce GHG emissions a specific amount by a target year:
Yes
None
List which emissions (scope 1, 2, and/or 3) are included in its GHG emissions commitment:
Scope 1, 2 & 3
None
The reduction level (percentage) institution has committed to:
100%
None
The baseline year the institution used in its GHG emissions commitment:
Jan. 1, 2007
None
The baseline emissions level institution used in its GHG emissions commitment:
15391
None
The target year the institution specified in its GHG emissions commitment :
Jan. 1, 2025
None
The website URL where information about the climate plan is available:
Data source(s) and notes about the submission:
---
The information presented here is self-reported. While AASHE staff review portions of all STARS reports and institutions are welcome to seek additional forms of review, the data in STARS reports are not verified by AASHE. If you believe any of this information is erroneous or inconsistent with credit criteria, please review the process for inquiring about the information reported by an institution or simply email your inquiry to stars@aashe.org.